TDOT Slates Pellissippi Parkway Extension Right-of-Way Meeting for Mid-2027 as Crews Re-Survey Corridor

BLOUNT COUNTY, Tenn. — The Tennessee Department of Transportation (TDOT) anticipates hosting a Right-of-Way Information Meeting in mid-2027 for property owners along the proposed Pellissippi Parkway (State Route 162) Extension corridor.

Although the extension was authorized for right-of-way funding in Federal Fiscal Year 2026, state officials confirmed that several critical technical steps remain before the agency is prepared to meet publicly with affected landowners.

According to written correspondence from John K. Barrett, P.E., TDOT Region 1 Highway Program Manager, the department had originally targeted January 2027 for the meeting. That timeline shifted slightly after the project was placed on hold while federal and local funding was secured and necessary updates to the Transportation Improvement Program (TIP) were completed.

Survey Updates and Phased Acquisitions

The extension project is currently projected to require approximately 91 right-of-way tracts encompassing nearly 200 acres of property for roadway construction. Because of the time needed to complete appraisals and limitations on available right-of-way agent resources, TDOT plans to acquire the tracts in sequential phases rather than all at once.

Before those buyouts can begin, TDOT survey teams are re-evaluating the entire route. The currently available right-of-way plans date back to 2022, and conditions on the ground have changed over the intervening years. Survey crews are cataloging recent property subdivisions, new buildings, sheds, and other structural improvements across the corridor.

This updated field data will be incorporated into revised right-of-way plans, which TDOT considers essential for determining the type of appraisals required and setting just compensation values for acquired land and improvements. Once finalized, the revised plans will allow TDOT to initiate title research, begin direct notifications to affected property owners, and announce a firm date for the public meeting.

Landowner Rights and Process Details

During the upcoming mid-2027 meeting, TDOT staff will outline the overall acquisition schedule, detail what owners can anticipate during each phase, and provide dedicated contact personnel to assist landowners through the process.

In the meantime, the department emphasized that property owners retain their full property rights: no restrictions exist on an owner’s ability to develop, sell, finance, or otherwise use their land prior to formal acquisition. Furthermore, while provisions exist for “hardship acquisitions,” Barrett noted these are reserved strictly for emergency or extraordinary circumstances and require specialized, restrictive approval from the Federal Highway Administration (FHWA).

BACKGROUND

The right-of-way acquisition process for the long-debated Pellissippi Parkway Extension in Blount County relies on an $11 million local cost-sharing agreement between municipal entities and TDOT, alongside key land contributions from the local economic development authority.

Under the intergovernmental funding framework finalized in mid-2026, TDOT required direct municipal financial participation to include right-of-way funding in the state’s 10-year transportation plan. The cash portion of the local obligation totals $10.97 million, distributed across three jurisdictions:

  • Blount County: Committing $5,000,000 total ($1.25 million annually over four years), formally approved by the Blount County Commission under Resolution 2607002 in July 2026 following heated public debate regarding project timing and fiscal priorities.
  • City of Maryville: Committing $3,900,000 total ($975,000 annually over four years).
  • City of Alcoa: Committing $2,070,000 total ($517,500 annually over four years).

In addition to municipal cash commitments, the Industrial Development Board of Blount County (IDB-BLOUNT) is providing $6,029,700 in donated land dedicated to the state’s needed right-of-way footprint. This donation provides a substantial portion of the land assembly required to extend the roadway corridor from State Route 33 to US-321 (Lamar Alexander Parkway).

Despite securing acquisition funding for Fiscal Year 2026, actual roadway construction remains scheduled in TDOT’s long-range plan for Fiscal Year 2036. The decade-long gulf between local right-of-way assembly and physical construction continues to draw close scrutiny from area residents, civic advocacy groups, and local municipal planners.


Discover more from TENNESSEE TRUTH LLC

Subscribe to get the latest posts sent to your email.

Leave a Reply

Your email address will not be published. Required fields are marked *

COPYRIGHT NOTICE & LEGAL DISCLAIMER © 2026 TENNESSEE TRUTH, LLC. All Rights Reserved. All content, journalism work products, interview transcripts, field notes, audio/video recordings, drafts, and investigative materials (collectively, the “Work Product”) are the sole and exclusive property of TENNESSEE TRUTH, LLC and are protected under United States and international copyright laws. Unauthorized reproduction, distribution, modification, or dissemination of this Work Product, in whole or in part, without express written permission is strictly prohibited.